Request from client
The development, production, and delivery of new rotating slats with modified imagery for 22 rotating locations on the A28. Why? Due to a change in the speed limit on the A28, the imagery on the rotating slats also had to be changed at all 22 locations.
Project progress: ''Rotatielamellen A28''
Sanne Bolder, Work Planner at BAM Infra Verkeerstechniek BV: 'The project went very well. Thanks to the excellent cooperation and proactive approach of AGMI Traffic & Lighting, the project was completed quickly and flawlessly.
We started with an inventory to get a clear picture of the existing situation, such as the direction of rotation, the dimensions, and the type of rotating panel. In order to carry this out according to plan, AGMI Traffic & Lighting drew up an inventory form with a clear checklist to obtain the necessary information for the new lamellas to be produced.
After a successful FAT in AGMI Traffic & Lighting's production facility, the slats were delivered and replaced according to plan.
Products supplied
New rotating slats for 22 rotation locations to replace the current slats.